WAHOOPool Aquatics
Valley Commercial Learn-to-Swim — Swim School Pools in Brisbane City, QLD

Case Study // Brisbane City, QLD

Valley Commercial Learn-to-Swim

Retrofitting a 25-metre programme pool into an existing industrial warehouse footprint.

2023Year
18 weeksDuration
25.0mLength
300 m³Volume

The Challenge

Engineering constraints the brief would not forgive.

Overcoming severe indoor ventilation challenges driven by high bather density and building a freestanding structural shell without excavating the leased warehouse slab — all while maintaining operational access for neighbouring tenancies.

The Applied Solution

How we engineered the answer.

We engineered a fully freestanding out-of-ground monolithic concrete vessel and installed high-output UV destructors combined with VSD pumps to hyper-turnover the water, keeping chloramine levels below detection threshold. The warehouse slab was never compromised.

What we delivered

  • Freestanding out-of-ground structural vessel design
  • Indoor air-quality management plan (UV + VSD)
  • Hyper-turnover filtration schedule
  • Acoustic treatment specification
  • Operator training and O&M manual

Measured Outcomes

Results that passed audit.

First-pass

Indoor air-quality audit

45 min

Turnover verified at 120% bather load

Zero

Warehouse slab disturbance

18 wk

Dual-shift delivery programme

Gallery

Project detail.

Plant room — UV destructor + VSD pump array
Plant room — UV destructor + VSD pump array
Freestanding above-ground structural vessel in warehouse shell
Freestanding above-ground structural vessel in warehouse shell