WAHOOPool Aquatics
Regional Municipal 50m Aquatics — Olympic Pools in South East Queensland

Case Study // South East Queensland

Regional Municipal 50m Aquatics

A complete FINA-certified 50m 8-lane competition pool accompanied by an indoor hydrotherapy tank.

2024Year
36 weeksDuration
50.020mLength
2,100 m³ main + 93 m³ hydroVolume

The Challenge

Engineering constraints the brief would not forgive.

Meeting the strict 50.020m dimensional tolerance required for state and national swimming records, whilst simultaneously delivering a clinical hydrotherapy tank sharing the same plant room — and doing so under full public-procurement transparency.

The Applied Solution

How we engineered the answer.

We deployed real-time laser theodolite surveying during the concrete shoot and tile setting, with sub-millimetre feedback to the finishing crew. End-wall touchpads were installed before final grout, aligned to ±2mm at 50m. Hydrotherapy thermal regulation ran on an independent titanium-heat-exchanger loop.

What we delivered

  • FINA dimensional survey (±20mm at 50m)
  • Electronic touch-pad integration specification
  • Hydrotherapy thermal regulation system
  • Tiered spectator slab structural interface
  • Community commissioning + swim-club training pack

Measured Outcomes

Results that passed audit.

50.017m

Actual dimensional audit result

±0.2°C

Hydrotherapy held at 34°C across 12-month DLP

FINA-certified

State competition-ready on handover

Zero

Structural rework over 36-week programme

Gallery

Project detail.

50m competition pool — lane markings + electronic touch-pads
50m competition pool — lane markings + electronic touch-pads